South Tower News
Forming, rebar and shotcrete for new shear walls are on hold until new area opens up on Level B/A & 1. Utility re-routing is ongoing in corridors and barricaded areas on Levels A thru 3. Finish work for New Histology space is complete. Starting Framing & Finishes in various locations.
Full story... School of Public Health News
Concrete placement for 2nd floor roof is complete. Formwork along exterior walls is underway. Interior wall framing, plumbing and ductwork installation is ongoing.
Full story... Semel News
Installation of new mechanical equipment on levels A and 2 is underway. Interior wall framing and drywall installation is continuing for the next several months. Elevator lobby work including new walls, floor and ceiling finishes is 25% complete.