CHS Construction Website Update - Week of September 11

All Demolition, Abatement, and Seismic Improvements are complete
Restoration of interior and exterior finishes is ongoing
Installation of new fire alarm system and pretesting is ongoing

Southeast Wing

Abatement: 100% complete
Demolition: 100% complete
Seismic Improvements: 100% complete
Restoration of Finishes: 98% complete
Fire Alarm: 99%

BioMed Library

Abatement: 100% complete
Demolition: 100% complete
Seismic Improvements: 100% complete
Restoration of Finishes: 93% complete
Fire Alarm: 99%

School of Medicine-East

Abatement: 100% complete
Demolition: 100% complete
Seismic Improvements: 100% complete
Restoration of Finishes: 70% complete
Fire Alarm: 97%

School of Medicine-W

Abatement: 100% complete
Demolition: 100% complete
Seismic Improvements: 100% complete
Restoration of Finishes: 42% complete
Fire Alarm: 83%

Exterior Expansion Joints

Demo: 100% complete
Structural: 100% complete
Framing: 100% complete
Expansion Joint Cover: 40% complete

Stair Re-opening and Closures

Stair 4 re-opened on September 11
Stair 6 is closed and will re-open late November

Archive

CHS Construction Website Update - Week of July 10

Southeast Wing

Abatement: 100% complete
Demo: 100% complete
Concrete: 100% complete
Fiberwrap: 100% complete
Seismic Bolting: N/A
Shotcrete: 100% complete
Finishes: 68% complete
Fire Alarm: 92%

BioMed Library

Abatement: 100% complete
Demo: 100% complete
Concrete: 100% complete
Fiberwrap: 100% complete
Seismic Bolting: 100% complete
Shotcrete: N/A
Finishes: 54% complete
Fire Alarm: 90%

School of Medicine-East

Abatement: 88% complete
Demo: 85% complete
Concrete: 85% complete
Fiberwrap: 70% complete
Seismic Bolting: 95% complete
Shotcrete: 90% complete
Finishes: 28% complete
Fire Alarm: 93%

School of Medicine-W

Abatement: 93% complete
Demo: 90% complete
Concrete: 65% complete
Fiberwrap: 52% complete
Seismic Bolting: N/A
Shotcrete: 100% complete
Finishes: 10% complete
Fire Alarm: 65% complete

Exterior Expansion Joints

Demo: 100% complete
Structural: 100% complete
Framing: 100% complete
Expansion Joint: 0% complete

Stair Re-opening and Closures

Stair 2 Re-opened on 6/7
Stair 1 closed to Re-open on 6/26
Stair 3 closed to Re-open mid-August

CHS Construction Website Update - Week of June 12

Southeast Wing

Abatement: 100% complete
Demo: 100% complete
Concrete: 100% complete
Fiberwrap: 100% complete
Seismic Bolting: N/A
Shotcrete: 100% complete
Finishes: 86% complete
Fire Alarm: 95%

BioMed Library

Abatement: 100% complete
Demo: 100% complete
Concrete: 100% complete
Fiberwrap: 100% complete
Seismic Bolting: 100% complete
Shotcrete: N/A
Finishes: 73% complete
Fire Alarm: 94%

School of Medicine-East

Abatement: 97% complete
Demo: 95% complete
Concrete: 93% complete
Fiberwrap: 89% complete
Seismic Bolting: 95% complete
Shotcrete: 100% complete
Finishes: 45% complete
Fire Alarm: 93%

School of Medicine-W

Abatement: 98% complete
Demo: 97% complete
Concrete: 88% complete
Fiberwrap: 64% complete
Seismic Bolting: N/A
Shotcrete: 100% complete
Finishes: 18% complete
Fire Alarm: 65% complete

Exterior Expansion Joints

Demo: 100% complete Structural: 100% comple
te
Framing: 100% complete
Expansion Joint Cover: 10% complete

Stair Re-opening and Closures

Demo: 100% complete
Structural: 100% complete
Framing: 100% complete
Expansion Joint Cover: 10% complete

CHS Construction Website Update - Week of May 15

Southeast Wing

Abatement: 100% complete
Demo: 100% complete
Concrete: 100% complete
Fiberwrap: 100% complete
Seismic Bolting: N/A
Shotcrete: 100% complete
Finishes: 45% complete
Fire Alarm: 89%

BioMed Library

Abatement: 100% complete
Demo: 100% complete
Concrete: 100% complete
Fiberwrap: 100% complete
Seismic Bolting: 100% complete
Shotcrete: N/A
Finishes: 26% complete
Fire Alarm: 65%

School of Medicine-East

Abatement: 80% complete
Demo: 75% complete
Concrete: 40% complete
Fiberwrap: 53% complete
Seismic Bolting: 88% complete
Shotcrete: 68% complete
Finishes: 8% complete
Fire Alarm: 89%

School of Medicine-W

Abatement: 80% complete
Demo: 75% complete
Concrete: 22% complete
Fiberwrap: 35% complete
Seismic Bolting: N/A
Shotcrete: 100% complete
Finishes: 0% complete
Fire Alarm: 65% complete

Exterior Expansion Joints

Demo: 100% complete
Structural: 85% complete
Framing: 90% complete
Expansion Joint: 0% complete

Stair Re-opening and Closures

Stair 14 Re-opened on 4/16
Stair 2 Closed on 4/17

CHS Construction Website Update - Week of May 2

Southeast Wing

Abatement: 100% complete
Demo: 100% complete
Concrete: 100% complete
Fiberwrap: 100% complete
Seismic Bolting: N/A
Shotcrete: 100% complete
Finishes: 38% complete
Fire Alarm: 85%

BioMed Library

Abatement: 100% complete
Demo: 100% complete
Concrete: 100% complete
Fiberwrap: 100% complete
Seismic Bolting: 100% complete
Shotcrete: N/A
Finishes: 23% complete
Fire Alarm: 55%

School of Medicine-East

Abatement: 75% complete
Demo: 70% complete
Concrete: 36% complete
Fiberwrap: 50% complete
Seismic Bolting: 84% complete
Shotcrete: 65% complete
Finishes: 5% complete
Fire Alarm: 83%

School of Medicine-W

Abatement: 75% complete
Demo: 70% complete
Concrete: 18% complete
Fiberwrap: 32% complete
Seismic Bolting: N/A
Shotcrete: 2% complete
Finishes: 0% complete
Fire Alarm: 62% complete

Exterior Expansion Joints

Demo: 100% complete
Structural: 80% complete
Framing: 75% complete
Expansion Joint: 0% complete

Stair Re-opening and Closures

Stair 14 Re-opened on 4/16
Stair 2 Closed on 4/17

CHS Construction Website Update - Week of April 3

Southeast Wing

Abatement: 100% complete
Demo:  100% complete
Concrete:  100% complete
Fiberwrap: 100% complete
Seismic Bolting: N/A
Shotcrete:  100% complete
Finishes: 22% complete
Fire Alarm: 80%

BioMed Library

Abatement: 100% complete
Demo:  100% complete
Concrete:  100% complete
Fiberwrap: 100% complete
Seismic Bolting: 100% complete
Shotcrete:  N/A
Finishes: 8% complete
Fire Alarm: 35%

School of Medicine-East

Abatement: 60% complete
Demo:  55% complete
Concrete:  20% complete
Fiberwrap: 35% complete
Seismic Bolting: 60% complete
Shotcrete:  55% complete
Finishes: 0% complete
Fire Alarm:  80%

School of Medicine-W

Abatement: 55% complete
Demo:  55% complete
Concrete:  6% complete
Fiberwrap: 20% complete
Seismic Bolting: N/A
Shotcrete:  0% complete
Finishes: 0% complete
Fire Alarm:  60% complete

Exterior Expansion Joints

Demo: 100% complete
Structural:  65% complete
Framing:  30% complete
Expansion Joint: 0% complete

CHS Construction Website Update - Week of February 6th

Southeast Wing

  • Abatement: 100% complete
  • Demo:  100% complete
  • Concrete:  77% complete
  • Fiberwrap: 80% complete
  • Seismic Bolting: N/A
  • Shotcrete:  100% complete
  • Finishes: 10% complete
  • Fire Alarm: 60%

BioMed Library

  • Abatement: 100% complete
  • Demo:  100% complete
  • Concrete:  75% complete
  • Fiberwrap: 33% complete
  • Seismic Bolting: 75% complete
  • Shotcrete:  N/A
  • Finishes: 5% complete
  • Fire Alarm: 10%

School of Medicine-East

  • Abatement: 20% complete
  • Demo:  20% complete
  • Concrete:  0% complete
  • Fiberwrap: 15% complete
  • Seismic Bolting: 10% complete
  • Shotcrete:  15% complete
  • Finishes: 0% complete
  • Fire Alarm:  60%

School of Medicine-W

  • Abatement: 10% complete
  • Demo:  10% complete
  • Concrete:  0% complete
  • Fiberwrap: 5% complete
  • Seismic Bolting: N/A
  • Shotcrete:  0% complete
  • Finishes: 0% complete
  • Fire Alarm:  0% complete

Exterior Expansion Joints

Demo: 100% complete

Structural:  5% complete

Framing:  0% complete

Expansion Joint: 0% complete

Construction Update Week of January 17

Southeast Wing

  • Abatement: 100% complete
  • Demo:  100% complete
  • Concrete:  65% complete
  • Fiberwrap: 65% complete
  • Seismic Bolting: N/A
  • Shotcrete:  100% complete
  • Finishes: 5% complete

BioMed Library

  • Abatement: 100% complete
  • Demo:  100% complete
  • Concrete:  50% complete
  • Fiberwrap: 33% complete
  • Seismic Bolting: 50% complete
  • Shotcrete:  N/A
  • Finishes: 5% complete

School of Medicine-East

  • Abatement: 15% complete
  • Demo:  15% complete
  • Concrete:  0% complete
  • Fiberwrap: 10% complete
  • Seismic Bolting: 10% complete
  • Shotcrete:  10% complete
  • Finishes: 0% complete

School of Medicine-W

  • Abatement: 5% complete
  • Demo:  5% complete
  • Concrete:  0% complete
  • Fiberwrap: 5% complete
  • Seismic Bolting: N/A
  • Shotcrete:  0% complete
  • Finishes: 0% complete

Construction Update Week of December 12

General Construction / Public Corridors & Lobbies –

  1. Ongoing installation of temporary hard wall enclosures
  2. Ongoing installation of new fire alarm system in the South East Wing, corridor work up to the top floor.  Office fire alarm devices will be installed over the next several months
  3. Ongoing relocation of overhead existing utilities located at the corridor seismic joints to facilitate the installation of structural upgrades
  4. Installation of fire alarm work will begin in the SOM-East, Vivarium in the Q1 of 2017


South East wing –

  1. Demolition and abatement is complete
  2. Installation of Fiber Reinforced Polymer at concrete columns and beams 95% complete
  3. Column and beam preparation for cast in place concrete 95% complete


Biomed Library –

  1. Seismic strengthening in study areas are ongoing
  2. drywall framing for partitions over seismic bolts in book stacks is 95% complete


Vivarium –

  1. Ongoing work at exterior expansion joint covers above Loading dock 1
  2. B, A and 1 level prep work at north and west shear walls is ongoing
  3. B level abatement and hard demolition complete


SOM East –

  1. Ongoing demolition and abatement primarily on Level B and A, select area on upper floors
  2. Prep work and research for the relocation of existing utilities all floors is ongoing


SOM West –

  1. Prep work and research for the relocation of existing utilities all floor
  2. Selective demolition at building expansion joints is underway


REED building –

  • Installation of new Fire Alarm system and Fire water standpipe conversion to begin Q2/Q3, 2017

Construction Update Week of November 7:

General Construction / Public Corridors & Lobbies –

  • Ongoing installation of new temporary hard partitions will be replacing the plastic enclosures which were used for abatement and demolition
  • Ongoing installation of new fire alarm system in the South East Wing, corridor work up to the 6thfloor
  • Ongoing relocation of overhead existing utilities located at the corridor seismic joints to facilitate the installation of structural upgrades
  • Installation of fire alarm work will begin in the SOM-East, Vivarium in the Q1 of 2017

South East wing

  • demolition is 90% complete
  • Installation of Fiber Reinforced Polymer at concrete columns and beams 70% complete
  • Column and beam preparation for cast in place concrete 65% complete

Biomed Library –

  • Removal of finishes in study area for preparation of cast in place concrete column strengthening
  • drywall framing for partitions over seismic bolts in book stacks is 25% complete

Vivarium –

  • Ongoing work at exterior expansion joint covers above Loading dock 1
  • B, A and 1 level prep work at north and west shear walls is ongoing
  • B level abatement and hard demolition ongoing
  • B level foundation saw cutting at shear walls is complete

SOM East –

  • Ongoing demolition and abatement primarily on Level B and A, select area on upper floors
  • Prep work and research for the relocation of existing utilities all floors

SOM West –

  • Prep work and research for the relocation of existing utilities all floors

REED building –

  • Installation of new Fire Alarm system and Fire water standpipe conversion to begin Q2/Q3, 2017

Construction Update Week of October 31:

General Construction / Public Corridors & Lobbies –

  • Ongoing installation of new temporary hard partitions will be replacing the plastic enclosures which were used for abatement and demolition
  • Ongoing installation of new fire alarm system in the South East Wing, corridor work up to the 6thfloor
  • Ongoing relocation of overhead existing utilities located at the seismic joints to facilitate the installation of structural upgrades
  • Installation of fire alarm work will begin in the SOM-East, Vivarium in the winter of 2017

South East wing

  • soft demolition is 85% complete
  • Installation of Fiber Reinforced Polymer at concrete columns and beams 65% complete
  • Column and beam preparation for cast in place concrete 50% complete

Biomed Library –

  • core drilling and seismic bolting complete in book stacks
  • drywall partitions over seismic bolts will begin this week

Vivarium –

  • Ongoing work at exterior expansion joint covers above Loading dock 1
  • B level abatement and hard demolition ongoing

SOM East –

  • Ongoing soft demolition in select areas
  • Prep work and research for the relocation of existing utilities

SOM West –

  • Prep work and research for the relocation of existing utilities

REED building –

  • Installation of new Fire Alarm system and Fire water standpipe conversion to begin early/mid 2017