CHS Construction Website Update - Week of February 6th

 

Southeast Wing

  • Abatement: 100% complete
  • Demo:  100% complete
  • Concrete:  77% complete
  • Fiberwrap: 80% complete
  • Seismic Bolting: N/A
  • Shotcrete:  100% complete
  • Finishes: 10% complete
  • Fire Alarm: 60%

 

BioMed Library

  • Abatement: 100% complete
  • Demo:  100% complete
  • Concrete:  75% complete
  • Fiberwrap: 33% complete
  • Seismic Bolting: 75% complete
  • Shotcrete:  N/A
  • Finishes: 5% complete
  • Fire Alarm: 10%

 

School of Medicine-East

  • Abatement: 20% complete
  • Demo:  20% complete
  • Concrete:  0% complete
  • Fiberwrap: 15% complete
  • Seismic Bolting: 10% complete
  • Shotcrete:  15% complete
  • Finishes: 0% complete
  • Fire Alarm:  60%

 

School of Medicine-W

  • Abatement: 10% complete
  • Demo:  10% complete
  • Concrete:  0% complete
  • Fiberwrap: 5% complete
  • Seismic Bolting: N/A
  • Shotcrete:  0% complete
  • Finishes: 0% complete
  • Fire Alarm:  0% complete

 

Exterior Expansion Joints

Demo: 100% complete

Structural:  5% complete

Framing:  0% complete

Expansion Joint: 0% complete

Archive

Construction Update Week of January 17

Southeast Wing

  • Abatement: 100% complete
  • Demo:  100% complete
  • Concrete:  65% complete
  • Fiberwrap: 65% complete
  • Seismic Bolting: N/A
  • Shotcrete:  100% complete
  • Finishes: 5% complete

BioMed Library

  • Abatement: 100% complete
  • Demo:  100% complete
  • Concrete:  50% complete
  • Fiberwrap: 33% complete
  • Seismic Bolting: 50% complete
  • Shotcrete:  N/A
  • Finishes: 5% complete

School of Medicine-East

  • Abatement: 15% complete
  • Demo:  15% complete
  • Concrete:  0% complete
  • Fiberwrap: 10% complete
  • Seismic Bolting: 10% complete
  • Shotcrete:  10% complete
  • Finishes: 0% complete

School of Medicine-W

  • Abatement: 5% complete
  • Demo:  5% complete
  • Concrete:  0% complete
  • Fiberwrap: 5% complete
  • Seismic Bolting: N/A
  • Shotcrete:  0% complete
  • Finishes: 0% complete

Construction Update Week of December 12

General Construction / Public Corridors & Lobbies –

  1. Ongoing installation of temporary hard wall enclosures
  2. Ongoing installation of new fire alarm system in the South East Wing, corridor work up to the top floor.  Office fire alarm devices will be installed over the next several months
  3. Ongoing relocation of overhead existing utilities located at the corridor seismic joints to facilitate the installation of structural upgrades
  4. Installation of fire alarm work will begin in the SOM-East, Vivarium in the Q1 of 2017


South East wing –

  1. Demolition and abatement is complete
  2. Installation of Fiber Reinforced Polymer at concrete columns and beams 95% complete
  3. Column and beam preparation for cast in place concrete 95% complete


Biomed Library –

  1. Seismic strengthening in study areas are ongoing
  2. drywall framing for partitions over seismic bolts in book stacks is 95% complete


Vivarium –

  1. Ongoing work at exterior expansion joint covers above Loading dock 1
  2. B, A and 1 level prep work at north and west shear walls is ongoing
  3. B level abatement and hard demolition complete


SOM East –

  1. Ongoing demolition and abatement primarily on Level B and A, select area on upper floors
  2. Prep work and research for the relocation of existing utilities all floors is ongoing


SOM West –

  1. Prep work and research for the relocation of existing utilities all floor
  2. Selective demolition at building expansion joints is underway


REED building –

  • Installation of new Fire Alarm system and Fire water standpipe conversion to begin Q2/Q3, 2017

Construction Update Week of November 7:

General Construction / Public Corridors & Lobbies –

  • Ongoing installation of new temporary hard partitions will be replacing the plastic enclosures which were used for abatement and demolition
  • Ongoing installation of new fire alarm system in the South East Wing, corridor work up to the 6thfloor
  • Ongoing relocation of overhead existing utilities located at the corridor seismic joints to facilitate the installation of structural upgrades
  • Installation of fire alarm work will begin in the SOM-East, Vivarium in the Q1 of 2017

South East wing

  • demolition is 90% complete
  • Installation of Fiber Reinforced Polymer at concrete columns and beams 70% complete
  • Column and beam preparation for cast in place concrete 65% complete

Biomed Library –

  • Removal of finishes in study area for preparation of cast in place concrete column strengthening
  • drywall framing for partitions over seismic bolts in book stacks is 25% complete

Vivarium –

  • Ongoing work at exterior expansion joint covers above Loading dock 1
  • B, A and 1 level prep work at north and west shear walls is ongoing
  • B level abatement and hard demolition ongoing
  • B level foundation saw cutting at shear walls is complete

SOM East –

  • Ongoing demolition and abatement primarily on Level B and A, select area on upper floors
  • Prep work and research for the relocation of existing utilities all floors

SOM West –

  • Prep work and research for the relocation of existing utilities all floors

REED building –

  • Installation of new Fire Alarm system and Fire water standpipe conversion to begin Q2/Q3, 2017

Construction Update Week of October 31:

General Construction / Public Corridors & Lobbies –

  • Ongoing installation of new temporary hard partitions will be replacing the plastic enclosures which were used for abatement and demolition
  • Ongoing installation of new fire alarm system in the South East Wing, corridor work up to the 6thfloor
  • Ongoing relocation of overhead existing utilities located at the seismic joints to facilitate the installation of structural upgrades
  • Installation of fire alarm work will begin in the SOM-East, Vivarium in the winter of 2017

South East wing

  • soft demolition is 85% complete
  • Installation of Fiber Reinforced Polymer at concrete columns and beams 65% complete
  • Column and beam preparation for cast in place concrete 50% complete

Biomed Library –

  • core drilling and seismic bolting complete in book stacks
  • drywall partitions over seismic bolts will begin this week

Vivarium –

  • Ongoing work at exterior expansion joint covers above Loading dock 1
  • B level abatement and hard demolition ongoing

SOM East –

  • Ongoing soft demolition in select areas
  • Prep work and research for the relocation of existing utilities

SOM West –

  • Prep work and research for the relocation of existing utilities

REED building –

  • Installation of new Fire Alarm system and Fire water standpipe conversion to begin early/mid 2017